The gas treatment plant (GTP) will be located in Prudhoe Bay near existing oil and gas infrastructure. The plant will be comprised of three process trains to remove impurities from the natural gas.
- An average daily capacity of 3.5 billion cubic feet; maximum capacity of 3.9 billion cubic feet per day.
- Carbon dioxide will be removed, captured, and provided for re-injection into underground reservoirs.